well here we are at the end of week 6 and the roof timber is going up, the whole house is now being surrounded with scaffolding (not so pretty) but it really seems to be happening now.Saturday, 17 July 2010
lots more timber
well here we are at the end of week 6 and the roof timber is going up, the whole house is now being surrounded with scaffolding (not so pretty) but it really seems to be happening now.blooming marvellous
Wednesday, 7 July 2010
lots of timber and an inspection visit



the computer has been down and i've been bereft without it, its back now but still slow - i think it might have to go eventually. anyway lots has happened here - i seem to have a daily meeting with david our builder making decisions that i truly hope are right. suddenly the timber walls have grown and we can walk through the rooms of the house. it now seems enormous. our very own chartered surveyor (ret'd) came to inspect and commented that it looked like a village hall!
Wednesday, 23 June 2010
wow we've got a floor



well an enormous crane arrived early this morning and two large lorries with blocks and beams followed by a floor-laying gang-loads of activity! the crane was so big the children at the primary school could see it - great excitement. by 2pm it was all done and dusted so everyone could run off to watch the football - lets hope england win today.the floor plan now looks much larger!
Friday, 18 June 2010
progress on the building site


its been dry all week so work on the site has progressed well, the blockwork has just about been done on the foundations, some work has been done on the drainage for the drive and the water pipe has been put in (but no water yet) apparently the floor will be done next week. at the moment the dimensions of the rooms look small i hope this will change as the build progresses otherwise we will be down-sizing!!